Hello,
I have a customer with a detached pool house that is currently being fed by utility service. The utility company has agreed to disconnect their underground lateral lines and let me splice into them below ground at both ends in order to use their lines for my new pool house feeder. This will mean that I only have to trench from the home to the utility transformer pad instead of trenching all the way to the pool house through dense woods with large deeply rooted trees. The only problem is that it is only three conductor. I was wondering if there is something written in the code that will let me use only three conductors for a 120/240-volt single phase feeder to a residential pool house.
Thanks,
I have a customer with a detached pool house that is currently being fed by utility service. The utility company has agreed to disconnect their underground lateral lines and let me splice into them below ground at both ends in order to use their lines for my new pool house feeder. This will mean that I only have to trench from the home to the utility transformer pad instead of trenching all the way to the pool house through dense woods with large deeply rooted trees. The only problem is that it is only three conductor. I was wondering if there is something written in the code that will let me use only three conductors for a 120/240-volt single phase feeder to a residential pool house.
Thanks,