ptonsparky
Tom
- Occupation
- EC - retired
I have an outside feeder going to one location with a total of eight pump panels. All SUSE and all are outside. Six involved in one process are hard wired. (Arguably one structure.) Two in another process serve cord & plug connected equipment because they are movable and temporary in nature. The customer wants to add a third seasonal cord and plug connected piece of equipment. (30 HP)
Do I, somehow, need to reduce the # of disconnects? Options?
Do I, somehow, need to reduce the # of disconnects? Options?