If your doing a typical 1 floor( 20k sq ft) office renovation with demo, conv receptacles/power(no feeders..just homeruns from panels), lighting, controls, security, IT and fire alarm I'd imagine there's a practical limit to the # of men you could put on the job in which they would be productive doing work. I'm having a hard time figurng that out in this situation.
With the hours I have and the timeframe they are giving( THEY DON'T WANT ANY OVERTIME) I have an average of 9 men. Would there be work available for an average of 9 men? This is where knowing how a job will be build and actually having done the installation helps a lot. Hope I'm making sense. I understand I could suggest more time but I wan't to make sure this work can't be done with 9 men. Thanks.
With the hours I have and the timeframe they are giving( THEY DON'T WANT ANY OVERTIME) I have an average of 9 men. Would there be work available for an average of 9 men? This is where knowing how a job will be build and actually having done the installation helps a lot. Hope I'm making sense. I understand I could suggest more time but I wan't to make sure this work can't be done with 9 men. Thanks.