RICHRICH36
Member
- Location
- Florida
I cant quite assemble the article numbers and I am second quessing myself but I was hoping someone else could reassure me.
Info
AHJ enforcing 2008 NEC
This is a temporary service for a remediation trailer.
My situation is:
I need to feed a "detached building" which is basically a pull behind trailer with the wheels removed and tied down and approved by building inspection. I need to feed this trailer with a 200A 3 Phase Delta service. This trailer has a permanently affixed 200A disconnect with 150A fuses in it. Trailer only requires a 150a service.
What I want to do:
Mount a 7 terminal 3 phase metercan on a 25' pole. Heres the kicker, I want to mount the metercan only. No disconnecting means at this point. I want to feed the trailer direct buried with 4/0 AL USE wire. At this point I will terminate in the 200A Disconnect which is fused at 150.
What I think I can reference:
Article 230.6 for conductors outside and/or article 240.101(B) for the "feeder tap" rule.
Does anyone have any objective reasons on why I couldnt do this?
Info
AHJ enforcing 2008 NEC
This is a temporary service for a remediation trailer.
My situation is:
I need to feed a "detached building" which is basically a pull behind trailer with the wheels removed and tied down and approved by building inspection. I need to feed this trailer with a 200A 3 Phase Delta service. This trailer has a permanently affixed 200A disconnect with 150A fuses in it. Trailer only requires a 150a service.
What I want to do:
Mount a 7 terminal 3 phase metercan on a 25' pole. Heres the kicker, I want to mount the metercan only. No disconnecting means at this point. I want to feed the trailer direct buried with 4/0 AL USE wire. At this point I will terminate in the 200A Disconnect which is fused at 150.
What I think I can reference:
Article 230.6 for conductors outside and/or article 240.101(B) for the "feeder tap" rule.
Does anyone have any objective reasons on why I couldnt do this?