newservice
Senior Member
- Location
- Syracuse NY
- Occupation
- Electrician extraordinaire
I feel embarrassed to ask but they finally got around to requiring the outside service disconnects here. So I'm about to put one in, Milbank meter- 200A disco breaker-combo unit, running my 4 wires to the main panel (which I will have to get used to calling a sub panel now). Having the panel breaker the same rating as the service breaker kind of worries me in case of an overload, which one trips first? Does it matter? Seems I recall that a feeder breaker should be larger than a subpanel breaker. Pretty unlikely to ever happen , just wondering if there's code for this, thanks,