Otis2011
Member
- Location
- Maumee, Ohio
I have been investigating the case of 3 Pole automatic transfer switches, single generator, and two 3P/4W buildings with dedicated LV transformers. I have come to the conclusion it is impossible to discuss without a one line sketch. See attached.
I have laboriously studied the 28 previous posts on the subject. Hoping to get some good clarification on the issue.
Basic question, is the proposed system one-line Code, not code (state 2011 NEC references with thoughts), an AHJ decision, other?
Thanks in advance.
I have laboriously studied the 28 previous posts on the subject. Hoping to get some good clarification on the issue.
Basic question, is the proposed system one-line Code, not code (state 2011 NEC references with thoughts), an AHJ decision, other?
Thanks in advance.