lakee911
Senior Member
- Location
- Columbus, OH
I have an existing 120/240V 4-wire open delta system that has one 25KVA transformer and one 50KVA transformer (with a center tap). I understand that the transformers will have only 58% of their typical capacity. What I'm not sure about is if it will be (25KVA+25KVA)*0.58 or 25KVA*0.58. I would think that it would be the first of the two , but I wanted to check.
To complicate the matter the 50KVA is serving out additional customers/services besides the one service using the three phase. So, if that load is more than the remaining 25KVA then my three phase power is then reduced, right?
Thanks,
Jason
To complicate the matter the 50KVA is serving out additional customers/services besides the one service using the three phase. So, if that load is more than the remaining 25KVA then my three phase power is then reduced, right?
Thanks,
Jason