Hi there,
I am engineer at a large utility. I assist folks with Overhead Open Delta transfornmer sizing, and we've developed a process to take customer panel schedules and size transformers. Our program is set up to look at load splits across each widning. Our practice is to place the power pot (transformer) across A-B and the liter pot (transformer) across A-C. For power pot sizing we take the load across A-B at 100% + three phase load at 58%. Additionally, for liter pot sizing we take the larger of the two (A-N or C-N) + the A-C load at 100% + three phase load at 58%.
The program works well, but has a few holes however. We see an occasional customer place two pole load across B-C. In the past I've asked folks to move to A-C or A-B, but I wanted to verify from some of the industry experts what would be the load split accross each transformer for load across B-C. Can I assume this is three phase load and convert it to 3-pole load? E.g. 30A/2P breaker across B-C with 2400VA per phase (at 120/240V). (2400VA X 2)/3 = 1600VA. If not how should I handle this load? It has to go someplace, granted too much load across B-C would possibly collapse the Delta. Question is how much is too much? We limit 3-phase peak demand to 50kVA and largest single motor to 25HP for these applications. Please advise.
Appreciate any help.
Regards,
Frank G.
I am engineer at a large utility. I assist folks with Overhead Open Delta transfornmer sizing, and we've developed a process to take customer panel schedules and size transformers. Our program is set up to look at load splits across each widning. Our practice is to place the power pot (transformer) across A-B and the liter pot (transformer) across A-C. For power pot sizing we take the load across A-B at 100% + three phase load at 58%. Additionally, for liter pot sizing we take the larger of the two (A-N or C-N) + the A-C load at 100% + three phase load at 58%.
The program works well, but has a few holes however. We see an occasional customer place two pole load across B-C. In the past I've asked folks to move to A-C or A-B, but I wanted to verify from some of the industry experts what would be the load split accross each transformer for load across B-C. Can I assume this is three phase load and convert it to 3-pole load? E.g. 30A/2P breaker across B-C with 2400VA per phase (at 120/240V). (2400VA X 2)/3 = 1600VA. If not how should I handle this load? It has to go someplace, granted too much load across B-C would possibly collapse the Delta. Question is how much is too much? We limit 3-phase peak demand to 50kVA and largest single motor to 25HP for these applications. Please advise.
Appreciate any help.
Regards,
Frank G.