I have a multiple story building for a total of 35units. 2 of those units are very large that has 2 ranges, 2 a/c, and 2 instant water heaters. The service for the building is a meter center that is 208/120V 3 phase. Most units ore getting 2 of 3 (single) 208/120 phase with a 225A panel (based on their load). For the 2 larger units that i have: i was thinking of doing 225A 3/phase 208/120V instead of 400A 208/120 2 of 3 hot (single). Is this it a better solution to do 3 phase 225 or go to a single 400A panel? I was thinking a 3phase 225 load center can still be recessed in some wall compared to a 400A single phase panel. Is there any violations of running a 3 phase to some of the condos that I'm missing?
Thank you
Thank you