the project is a 28 kw gen, 480 3ph,
want to run 300' feeder to 15kva xfmr 480/208/120wye, tap the feeder for 480v 3ph 5 ton hvac /elec heat 10000/830=12a
xfmr load secondary is lights and receptacles in a room 1000sqft
i want to feed a 3 phase load center to balance my load on the gen, the calculated load is ,<60a
15000/830=18a pri
15000/360=41a sec
question, does this smell good?
any comments or suggestions?
want to run 300' feeder to 15kva xfmr 480/208/120wye, tap the feeder for 480v 3ph 5 ton hvac /elec heat 10000/830=12a
xfmr load secondary is lights and receptacles in a room 1000sqft
i want to feed a 3 phase load center to balance my load on the gen, the calculated load is ,<60a
15000/830=18a pri
15000/360=41a sec
question, does this smell good?
any comments or suggestions?