I just quoted a 300X1200 building this week and found the other bidder quoted 5 different service entrances. Were is the exception in the code that allows him to build it that way?
Also potentially 230.2(B)?230.2(C)(1)
That's it. Thanks!230.2(C)(1)
The owner would need to see what POCO would charge for that when evaluating bids using different designs.It's a design build job. He quoted three 1200a services on one side of the building and two 1200a services on the opposite side of the building. He wants the owner to get the power company to feed these services with 5 different pad mounted transformers.
It's a design build job. He quoted three 1200a services on one side of the building and two 1200a services on the opposite side of the building. He wants the owner to get the power company to feed these services with 5 different pad mounted transformers.