hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
Please read entire before going to questions.
Attached sketches is showing apartment complex one cluster with building #1,2,3,4,5,6,7,8. One sketch is top view and another is elevation view.
Each building is three levels with attic and has dwelling units except building #2 and #4 which has electric room as well as dwelling units.
Sketch show each building is joined and separated by firewall. So building #1 separate building #2 by firewall same between building #2 and #3, building #3 and #4 etc
Both Fire protection engineer and Architect say they consider each building separate building. Building #1 is separate from #2, building #2 separate from #3 etc.
Attached sketches also shows outside POCO utility transformer feeding service switchboard outside. From service switchboard have one outside feeder FDR #1 going to Panel A. Panel A is attached to exterior wall of Building #3. Panel A then has two feeders go up the exterior walls of Building #3, go inside attic and then go to building #2, #4 attic and drop down to electric rooms and to meter stacks. The meter stacks feed buildings #1 to #8 dwelling units panelboards.
Question:
1. Each building #1 to #8 are consider separate buildings as stated by Architect and fire protection engineer. Can one outside feeder FDR#1 feed multiple buildings building #1 to #8 as shown in sketch thru panel A or not? I read NEC 2014 section 225.30 but I am confused a building can be fed by one feeder but in this case I am not sure if one feeder can fed multiple buildings or not.
2. Would plaques be required in electric rooms buildings #2,#4 or not?
Attached sketches is showing apartment complex one cluster with building #1,2,3,4,5,6,7,8. One sketch is top view and another is elevation view.
Each building is three levels with attic and has dwelling units except building #2 and #4 which has electric room as well as dwelling units.
Sketch show each building is joined and separated by firewall. So building #1 separate building #2 by firewall same between building #2 and #3, building #3 and #4 etc
Both Fire protection engineer and Architect say they consider each building separate building. Building #1 is separate from #2, building #2 separate from #3 etc.
Attached sketches also shows outside POCO utility transformer feeding service switchboard outside. From service switchboard have one outside feeder FDR #1 going to Panel A. Panel A is attached to exterior wall of Building #3. Panel A then has two feeders go up the exterior walls of Building #3, go inside attic and then go to building #2, #4 attic and drop down to electric rooms and to meter stacks. The meter stacks feed buildings #1 to #8 dwelling units panelboards.
Question:
1. Each building #1 to #8 are consider separate buildings as stated by Architect and fire protection engineer. Can one outside feeder FDR#1 feed multiple buildings building #1 to #8 as shown in sketch thru panel A or not? I read NEC 2014 section 225.30 but I am confused a building can be fed by one feeder but in this case I am not sure if one feeder can fed multiple buildings or not.
2. Would plaques be required in electric rooms buildings #2,#4 or not?
Last edited: