I have utility poles on plant site delivering 34.5kV and 12.47kV.
We are in the process of designing an outdoor process conveyor. Some of the poles/wires pose an interference.
Solution: Route overhead lines underground in a couple of places via duct banks. Underground runs would be approx. 150 feet.
I understand that the utility owns the lines. By going up and down with lines...do I need to be concerned with power quality, code implications (I believe utility companies have their own code), maintenance?
Is this standard practice...am I being too paranoid?
We are in the process of designing an outdoor process conveyor. Some of the poles/wires pose an interference.
Solution: Route overhead lines underground in a couple of places via duct banks. Underground runs would be approx. 150 feet.
I understand that the utility owns the lines. By going up and down with lines...do I need to be concerned with power quality, code implications (I believe utility companies have their own code), maintenance?
Is this standard practice...am I being too paranoid?