I work in a jurisdiction known not only for crossing t's and dotting i's but being particular about the shape of the dot on the i .
We're looking at spot N for a new panel in a 1960's building. A and B are existing 240V single phase panels.

I see Mike Holt's letter "Working Clearances, based on the 2020 NEC" that says overlap is fine,
but I don't see any NEC section that explicitly allows it.
The equipment has a removable, no hinge door.
What can I use to back myself up, in case this AJH calls it out? Does it seem OK to you?