There is an existing single phase 480/240 15KVA Transformer. At this time it is primary only protected. All that was being fed by it was two 120 volt receptacles for two small heater motors. Is there any issue installing a 125 Amp panel? Or should it be no larger than a 50 amp panel? The transformer secondary is 62.5 Amperes. At this time the load will only be a couple amperes. But no telling what might be added later as this is in an industrial plant.