I have panelboard 120/208V single phase in serving area of pizza restaurant. The panelboard has 3 feet clearance but serving area will have people walking in front of the working space and that space is going to be busy. Measuring from panelboard right at 3 feet ends their is the serving platform so whoever is serving would be standing in working space of panelboard and the panelboard would be behind the person. To the left of the panelboard but not in working space their is the dough machine.
I am not sure if above can satisfy working space clearance or does it need to be relocated?
I am not sure if above can satisfy working space clearance or does it need to be relocated?