PbMXer_218
Member
- Location
- Largo, Florida
- Occupation
- Licensed Electrician EC
Can anyone give a code reference about panels connected to an emergency system must be fully rated? We recently submitted some switch gear submittals that were returned noted. The comment stated "NEC requires panels connected to an emergency system to be fully rated". I am not trying to argue this, however, we have done many of this exact buildings and have never had this comment before. I have looked but cannot seem to find the code they are referencing.