Need some advise Please! There's a 6750 sq ft house being built (nearly complete)and now they find out there there short of circuit breakers. Here is the breakdown---320 amps from Comm-Ed to the meter enclosure, 2) 200 amp 40 space panels completely full, contractor wants to add another 200 amp 40 space panel off the existing 320 amp, I told him NO. Does anyone AGREE or DISAGREE? Can you site NEC articles either way? There were no calculations done by anyone. Alot of add-ons. Thanks Denny