I have one riser with 600kcm aluminum coming down that’s going to parallel 4/0 aluminum to two meters (all one enclosure). Out of each side of the meter I’ll have service disconnects with feeders to 2 separate units of a building (each with their own panel) I’ve seen multiple people including my inspector say that I can tie my GEC from each disconnect together and then run a common GEC to a ground rod. Wouldn’t this create a parallel path for my neutral to flow since my N-G bond occurs in each disconnect? Also if this is okay and I’m incorrect how do I size my common GEC? I know it applies to note 1 of Table 250.66 NEC but I can’t understand which “pair” or ungrounded conductors I’m supposed to size it off of.