I have a 25kw commercial ballasted system. 14.4kw and 9kw Solar Edge string inverters with rooftop Solar Edge power optimizers/rapid shut down units and Lg 406w modules.
Under the NEC 2017 code, since I will be passing the DC circuits (using #10PV wire and 12amp/circuit max) thru a roof to the transformerless inverters, can i skip any fuses and box or circuit disconnects and just use pass-thru boxes like Cooper CrouseHinds units for wire type changes?
Same question for NEC 2020.
Under the NEC 2017 code, since I will be passing the DC circuits (using #10PV wire and 12amp/circuit max) thru a roof to the transformerless inverters, can i skip any fuses and box or circuit disconnects and just use pass-thru boxes like Cooper CrouseHinds units for wire type changes?
Same question for NEC 2020.