Hello,
I am a long time lurker, but a first time poster! I am working on a project for a FSO (floating storage and offload) barge which stores crude oil. I have some equipment to install in the Division 1 area and need a way to pass an appropriately rated cable through a steel bulkhead. One side of the bulkhead is C1D1 rated and the other is a safe area. Any thoughts on the right way to do this? I am kind of envisioning a "myers hub-esque" fitting with a cable gland on each side of the bulkhead.
Thanks,
Dave
I am a long time lurker, but a first time poster! I am working on a project for a FSO (floating storage and offload) barge which stores crude oil. I have some equipment to install in the Division 1 area and need a way to pass an appropriately rated cable through a steel bulkhead. One side of the bulkhead is C1D1 rated and the other is a safe area. Any thoughts on the right way to do this? I am kind of envisioning a "myers hub-esque" fitting with a cable gland on each side of the bulkhead.
Thanks,
Dave