Permits

Status
Not open for further replies.

enerconn1

Member
Has anyone ever recieed a permit for there building on a yearly basis to cover minor repairs and ballast replacemants and installation of branch circuits and if so what was your process and did the local authority understand what you were wanting or was it difficult.
 

BAHTAH

Senior Member
Location
United States
Re: Permits

In my area the building dept would issue yearly permits to manufacturing facilities that had a qualified person on staff. This was to avoid having to issue permits for every little project. I think there was some dollar value that determined when a separate permit was required so you could not do a building addition or major work undere the yearly permit. The building department would then make a general inspection twice a year. You should check with your local AHJ to see if such a program is available.
 