Physical Damage vs Severe Physical Damage (EMT vs RMC)

Status
Not open for further replies.

Elect117

Senior Member
Location
California
Occupation
Engineer E.E. P.E.
344.10(E) - RMC is suitable in locations where SEVERE damage may occur.

358.10(E) - EMT is suitable in locations where physical damage may occur.

What locations would have severe physical damage?

If I wanted to wire a light through a table saw, is that severe physical damage? Like RMC can be used on the floor where forklifts can drive over it without a ramp?

I don't understand what the distinction between the two is supposed to ensure. I wonder if someone knows how to find the discussion notes on the code change. Maybe they included an example? I just can't think of a scenario that is severe physical damage in which RMC is an application.
 
I'm not sure if there is an actual NEC definition of severe damage but IMO an area where the raceway could be impacted by a motor vehicle would meet the definition. Here in the Northeast if you used EMT out of a meter over a sidewalk instead of SE cable that would qualify as a location where physical damage may occur from something like a snow shovel or a snow blower.
 
I'm not sure if there is an actual NEC definition of severe damage but IMO an area where the raceway could be impacted by a motor vehicle would meet the definition. Here in the Northeast if you used EMT out of a meter over a sidewalk instead of SE cable that would qualify as a location where physical damage may occur from something like a snow shovel or a snow blower.

Ya, so what is severe, you know?

If EMT can hand a snow shovel then what is so severe that EMT couldn't handle it but RMC could?

It is such a weird line to draw given neither "severe physical damage" or "physical damage" are defined by any metric.

The only instances I can think of are hazardous locations which specify their wiring method anyway. Like inside a commercial cooking process (not really physical damage) and near milling or mining equipment.

So, as a theoretical, what stops someone from using RMC with conductors inside as a speed bump in a parking lot? lol
 
I've asked the same question recently. If the plans are drawn by an engineer, then that would be a great time for an RFI. If you're in an area where the inspectors work with you instead of against you, then you might be able to have a pre-con meeting with them. If you don't CYA on things like this, you can sure spend a lot of money later. I've done distribution centers for Dollar Tree and Walmart. They have forklifts buzzing everywhere and if you use EMT on anything under 6' AFF, IMO that's a crushing hazard.
 
Opinion here, but I think it comes down to knowing the material and what it can realistically handle. Huge gray area, there are way too many variables.
 
Status
Not open for further replies.
Top