fandi
Senior Member
- Location
- Los Angeles
Hello All,
We have a N.O. 4000A tie breaker of a twin 4000A switchboards (they're identical switchboard with same ground, installed at the same time). Each swbd is fed from each utility transformer. One of the transformer is being demo'd due to light loads at the facility and a new cogen to feed both swbds.
To combine the two swbds into one, the N.O. tie breaker needs to be converted to N.C. breaker.
At this time, the cogen is not being connected to the swbds yet. We simply turn off the main breaker of the swbd which its upstream transformer will be demo'd and close the tie breaker. Per the peak demand in the latest year electric bill, the remaining transformer should handle two swbds combined (we don't plan to add significant loads in the future) but we still want to make sure to come up with a sequence of operation of permanently closing the tie breaker.
Any input idea would be highly appreciated!
Thanks a lot.
We have a N.O. 4000A tie breaker of a twin 4000A switchboards (they're identical switchboard with same ground, installed at the same time). Each swbd is fed from each utility transformer. One of the transformer is being demo'd due to light loads at the facility and a new cogen to feed both swbds.
To combine the two swbds into one, the N.O. tie breaker needs to be converted to N.C. breaker.
At this time, the cogen is not being connected to the swbds yet. We simply turn off the main breaker of the swbd which its upstream transformer will be demo'd and close the tie breaker. Per the peak demand in the latest year electric bill, the remaining transformer should handle two swbds combined (we don't plan to add significant loads in the future) but we still want to make sure to come up with a sequence of operation of permanently closing the tie breaker.
Any input idea would be highly appreciated!
Thanks a lot.