brantmacga
Señor Member
- Location
- Georgia
- Occupation
- Former Child
Question on something I'm not entirely familiar with;
We have a mechanical room. Inside of this room are my 3 panels (flush mounted, metal enclosure/cover), two air handlers, air cleaner, alarm panel, and LV rack with network equipment, lighting system controllers, and distributed audio.
The mechanical contractor ran the returns to this room, and installed grilles in the ceiling, so the room is now an air handling space. There is a return duct that goes into an air cleaning system, which then pumps the clean air back into the room for the air handler to pickup and distribute back out.
From what I read, my panels are fine, but there is a lot of LV cabling that comes out of the wall and into the back of the rack. Is this requires to be plenum rated cable?
This was all design-build with no plans or specs, just a floor plan to work off. I did not do the LV install. This was a collaborative effort with an LV contractor. I'm asking though because we have a similar project going together where we were turned down because the mechanical contractor made the entire attic an air handling space, and they did not use plenum rated cable. The mechanical contractor is now running return ducts to all the air handlers, which I'm pretty certain they are going to rip out after the final. They said the system is not designed for and will not operate as intended using return ducts. They asked me to come back and install smoke shutdowns across the attic.
Anyway, this AHJ does not issue separate LV permits, but they will inspect LV when they come to look at mine, and will not issue a CO if the LV is not to code.
Long winded I know ...... thanks
Sent from my iPhone using Tapatalk
We have a mechanical room. Inside of this room are my 3 panels (flush mounted, metal enclosure/cover), two air handlers, air cleaner, alarm panel, and LV rack with network equipment, lighting system controllers, and distributed audio.
The mechanical contractor ran the returns to this room, and installed grilles in the ceiling, so the room is now an air handling space. There is a return duct that goes into an air cleaning system, which then pumps the clean air back into the room for the air handler to pickup and distribute back out.
From what I read, my panels are fine, but there is a lot of LV cabling that comes out of the wall and into the back of the rack. Is this requires to be plenum rated cable?
This was all design-build with no plans or specs, just a floor plan to work off. I did not do the LV install. This was a collaborative effort with an LV contractor. I'm asking though because we have a similar project going together where we were turned down because the mechanical contractor made the entire attic an air handling space, and they did not use plenum rated cable. The mechanical contractor is now running return ducts to all the air handlers, which I'm pretty certain they are going to rip out after the final. They said the system is not designed for and will not operate as intended using return ducts. They asked me to come back and install smoke shutdowns across the attic.
Anyway, this AHJ does not issue separate LV permits, but they will inspect LV when they come to look at mine, and will not issue a CO if the LV is not to code.
Long winded I know ...... thanks
Sent from my iPhone using Tapatalk