Working on a residential service upgrade in San Diego. POCO allowed us to run the upgrade to the nearest hand hole which is accessible vs running to the nearest transformer which is much more complicated. They ran the calcs and gave us the greenlight.
Got trench approval and opened up the hand hole today to find 3 phase 3/0 AL. Am I correct in assuming they're tapping a phase of 3/0 to run our upgrade? Is that standard practice? Seems way underrated for a 400 amp service... especially given that this is a multi family dwelling upgrade with will be using a substantial % of available power with electric conversions and EV charging.
At this point there's no turning back for us, but I'm trying to prepare for possible issues when they come back out to pull and terminate.
Got trench approval and opened up the hand hole today to find 3 phase 3/0 AL. Am I correct in assuming they're tapping a phase of 3/0 to run our upgrade? Is that standard practice? Seems way underrated for a 400 amp service... especially given that this is a multi family dwelling upgrade with will be using a substantial % of available power with electric conversions and EV charging.
At this point there's no turning back for us, but I'm trying to prepare for possible issues when they come back out to pull and terminate.