Can a pool equipment panel board be supplied but another panel board that is not the service equipment? The situation I am asking about is in a completely new building, so the exception in 680.25(B) does not apply.
I have a dwelling with a 400 amp main feed through disconnect feeding (via compliant tap) 2- 200 amp MLO panels using feeders complying with 680.25(A), then off one of those MLO panels the pool equipment panel board is feed with feeders complying with 680.25. Does this installation comply with 680.25(B)?
I am being told it does not comply because the pool equipment panel board feeder does not originate at the service equipment. Is this the most common interpretation?
I have a dwelling with a 400 amp main feed through disconnect feeding (via compliant tap) 2- 200 amp MLO panels using feeders complying with 680.25(A), then off one of those MLO panels the pool equipment panel board is feed with feeders complying with 680.25. Does this installation comply with 680.25(B)?
I am being told it does not comply because the pool equipment panel board feeder does not originate at the service equipment. Is this the most common interpretation?