Senior Member
Presuming that the flammable gas is needed to complete commissioning.
The task of pouring seals can be completed prior or post startup, checkout or commissioning. 500.7(A) requires the seals be poured prior. Are there any industry accepted practices that permit seals be poured after bringing flammable gas and after commissioning?
500.7 offers twelve Protection Techniques. What are 500.7(L) Other Protection Techniques?
Lastly, when does your Company or your Customers pour seals?