PhaseShift
Senior Member
I'm in the process of designing a service feed to a remote location in order to provide power for various equipment. At the remote location I am told that I need (2) 110V 30A receptacles for tools as well as (1) 240V 20A receptacle for a battery charger. Adding this up tells me that I have 12kVA worth of load.
At the same location there is plans for a future load of 5kVA at 120V.
Because of the distance I am going to run a 480V service from an MCC out to this location where I will put a cabinet. I'm trying to decide weather it would be better to have the 480V feed two seperate 480 to 120/240V transformers for the two sets of loads or have one larger transformer and have a panel or something. If I go with the first option I will have a 12kVA transformer for the first set of loads and a 5kVA transformer for the second set of loads. If I go with the second option I will have (1) 17kVA transformer to serve all of the loads. Keep in mind the transformers can not get too large because I have to fit them in an outdoor cabinet.
The 5kVA load is something that is not yet planned and may never happen but I want to have the service avaliable for it. I want to factor this in the decision making for the economical aspect of the design.
Which of the two design choices do you guys think works the best?
At the same location there is plans for a future load of 5kVA at 120V.
Because of the distance I am going to run a 480V service from an MCC out to this location where I will put a cabinet. I'm trying to decide weather it would be better to have the 480V feed two seperate 480 to 120/240V transformers for the two sets of loads or have one larger transformer and have a panel or something. If I go with the first option I will have a 12kVA transformer for the first set of loads and a 5kVA transformer for the second set of loads. If I go with the second option I will have (1) 17kVA transformer to serve all of the loads. Keep in mind the transformers can not get too large because I have to fit them in an outdoor cabinet.
The 5kVA load is something that is not yet planned and may never happen but I want to have the service avaliable for it. I want to factor this in the decision making for the economical aspect of the design.
Which of the two design choices do you guys think works the best?
