D Daggerdale Member Nov 28, 2007 #1 What would be a realistic power factor value to use in planning a new service to an acute care hospital; +-600,000 square foot.
What would be a realistic power factor value to use in planning a new service to an acute care hospital; +-600,000 square foot.
zog Senior Member Location Charlotte, NC Nov 28, 2007 #2 You will need to provide alot more info before anyone can give you a ballpark value. Lets start at 0.5 - 1.0 and narrow it down from there.
You will need to provide alot more info before anyone can give you a ballpark value. Lets start at 0.5 - 1.0 and narrow it down from there.
kingpb Senior Member Location SE USA as far as you can go Occupation Engineer, Registered Nov 28, 2007 #3 Most utilities will penalize you for a PF lower then 0.85 lagging. I would start there. It has always been a good rule of thumb.
Most utilities will penalize you for a PF lower then 0.85 lagging. I would start there. It has always been a good rule of thumb.