malachi constant
Senior Member
- Location
- Minneapolis
We have an existing installation where the utility brings 13.8kV into the building. From there we have a lineup of MV switches that distribute out to transformer vaults within the facility (all one building, not a campus). These vaults contain (3) 1P cans that we are replacing with dry type 13.8k:208V equipment. Do these need to have additional primary protection within the vault (i.e. in sight of the transformer), or does the primary switch back at the service suffice? A question from a vendor has got me looking to verify, but I haven't found anything requiring it in NEC 240 or 450. Thanks!