I am a Building Official in N Florida and all my subject matter experts are not returning to work until after the 1st of the year.
I have a meter that is grounded but there is no ground running to the main disconnect/panel. The feeders are fed to the main panel protected by PVC conduit.
The main panel also has a bonding screw.
It seems like the ground wire should extend to the main panel and disconnect?
I look forward to your opinions!
Happy New Year!