mstrlucky74
Senior Member
- Location
- NJ
Example" NECA normal labor column calls for 54 hours per thousand for 1/C 750 kcmil THHN. I assume they came up with that unit based on pulling 3 or 4 wires at a time. If you have 1000' point to point and three 750's you a have( according to NECA units) 162 hours to make that pull. I know you never pull 1 or 2 large size wires but wouldn't the labor be about the same if you'd pull 1-2 or if you pull 3-4? They get pulled together ...but you would have double the labor depending.