curt swartz
Electrical Contractor - San Jose, CA
- Location
- San Jose, CA
- Occupation
- Electrical Contractor
I’m interested in getting some comments regarding about and upcoming project.
I went to a meeting yesterday with a builder to discuss the power supply for a new single-family dwelling. This project will be off the grid due to the cost of getting utility power to the site and the owner would prefer not having any utility power.
I have worked on off grid projects before that used traditional batteries and multiple parallel Outback inverters that were designed for the purpose. This projects is a little different since they will be using a battery system and inverter that is normally used for grid tie systems. The PV system that will supply power will utilizes a grid tie inverter.
There are 3 companies involved with this system.
(1) The company designing the battery system with its inverter.
(2) The PV company that will supply the PV system and its inverter. They will also supply all the other required equipment to complete the system.
(3) My company taking the power to the home.
The PV company and I were discussing where their work should end and my work should start. The Battery inverter and PV inverter for this system are only available in 3 phase 480. There will be a transformer to step the voltage down. The PV contractor agreed that I should supply the transformer and all wiring past it.
The engineer for the battery company said the I must use a 480 wye primary and delta secondary. He said the primary must be wye since this system is not tied to the grid and needs the neutral point for the inverters to work correctly. I said that is fine but I need a wye secondary to supply the house. He responded that that system will not work with a wye secondary. I asked if we could use a transformer with a wye primary and wye secondary and he said that will not work. If I need a wye secondary 2 transformers must be used.
Essentially, we have an ungrounded 480 source that needs a ground reference but at the same time we also need to reduce the voltage. I know there are zig-zag transformers that can be used for the ground reference, but wouldn’t that be the same as using a wye primary? If so why couldn’t the secondary of the transformer also be wye to avoid using a second transformer?
Since this is going way beyond my expertise the PV company and Battery supplier said they will work on a solution but I though I would ask here how a system like this should be designed to satisfy my own curiosity.
I went to a meeting yesterday with a builder to discuss the power supply for a new single-family dwelling. This project will be off the grid due to the cost of getting utility power to the site and the owner would prefer not having any utility power.
I have worked on off grid projects before that used traditional batteries and multiple parallel Outback inverters that were designed for the purpose. This projects is a little different since they will be using a battery system and inverter that is normally used for grid tie systems. The PV system that will supply power will utilizes a grid tie inverter.
There are 3 companies involved with this system.
(1) The company designing the battery system with its inverter.
(2) The PV company that will supply the PV system and its inverter. They will also supply all the other required equipment to complete the system.
(3) My company taking the power to the home.
The PV company and I were discussing where their work should end and my work should start. The Battery inverter and PV inverter for this system are only available in 3 phase 480. There will be a transformer to step the voltage down. The PV contractor agreed that I should supply the transformer and all wiring past it.
The engineer for the battery company said the I must use a 480 wye primary and delta secondary. He said the primary must be wye since this system is not tied to the grid and needs the neutral point for the inverters to work correctly. I said that is fine but I need a wye secondary to supply the house. He responded that that system will not work with a wye secondary. I asked if we could use a transformer with a wye primary and wye secondary and he said that will not work. If I need a wye secondary 2 transformers must be used.
Essentially, we have an ungrounded 480 source that needs a ground reference but at the same time we also need to reduce the voltage. I know there are zig-zag transformers that can be used for the ground reference, but wouldn’t that be the same as using a wye primary? If so why couldn’t the secondary of the transformer also be wye to avoid using a second transformer?
Since this is going way beyond my expertise the PV company and Battery supplier said they will work on a solution but I though I would ask here how a system like this should be designed to satisfy my own curiosity.