pvgreeze
Member
- Location
- Philadelphia
- Occupation
- Electrical Engineer
Hi everyone,
I'm very new to PV design, and I have run up against a couple of problems that I could use some advice on.
I'm working on a solar system design in a building with a brand new electrical service. The main electrical engineer sent me his plans, and it looks like he is using the NEC 230.40 Exception 2 in his main distribution panel (MDP). There are two planned circuits off MDP (800A and 400A), two spaces for spares, and a dedicated section for our PV interconnection (load side of an 800A breaker). My question is, without a single utility disconnection point, could this solar design be rejected from an interconnection perspective? Technically, we would still be under six disconnecting points, as spelled out in the NEC. I apologize if this is a very basic/easy question, but I just was not sure, and I do not really have many other engineering resources to turn to within the office I work at.
Thanks in advance!!
PVG
I'm very new to PV design, and I have run up against a couple of problems that I could use some advice on.
I'm working on a solar system design in a building with a brand new electrical service. The main electrical engineer sent me his plans, and it looks like he is using the NEC 230.40 Exception 2 in his main distribution panel (MDP). There are two planned circuits off MDP (800A and 400A), two spaces for spares, and a dedicated section for our PV interconnection (load side of an 800A breaker). My question is, without a single utility disconnection point, could this solar design be rejected from an interconnection perspective? Technically, we would still be under six disconnecting points, as spelled out in the NEC. I apologize if this is a very basic/easy question, but I just was not sure, and I do not really have many other engineering resources to turn to within the office I work at.
Thanks in advance!!
PVG