Preliminary planning of a large (~1-3 MW ; 12.47kV Interconnect) PV Plant.
I'm assuming the 3MVA power transformer would be the long lead time (8-12 mths) item, but not being familiar with PV systems, might the inverter(s), panels, etc. exceed a 1 yr lead time?
We are considering doing the project in 2 stages:
Stage 1: Engineer / Design the Infrastructure (from the 480V/12.47kV PV Plant transformer - Upstream to the 69kV Utility PCC) (to include interconnection study / application)
Stage 2: PV Plant Design / Construction (Connect to 480V/12.47kV xfmr)
Many reasons for this, some economical, some restrictions, and buying time (if PV is not economical justifiable, installation of another renewable or alternate energy source - tied into the 3MVA infrastructure system designed in Stage 1).
So... perhaps I have 2 questions. From a big picture overview, anything objectionable to this plan?
Thanks!
I'm assuming the 3MVA power transformer would be the long lead time (8-12 mths) item, but not being familiar with PV systems, might the inverter(s), panels, etc. exceed a 1 yr lead time?
We are considering doing the project in 2 stages:
Stage 1: Engineer / Design the Infrastructure (from the 480V/12.47kV PV Plant transformer - Upstream to the 69kV Utility PCC) (to include interconnection study / application)
Stage 2: PV Plant Design / Construction (Connect to 480V/12.47kV xfmr)
Many reasons for this, some economical, some restrictions, and buying time (if PV is not economical justifiable, installation of another renewable or alternate energy source - tied into the 3MVA infrastructure system designed in Stage 1).
So... perhaps I have 2 questions. From a big picture overview, anything objectionable to this plan?