Pete Olson
Member
- Location
- Utah
- Occupation
- Electrical PM
We are currently estimating a project, the Engineer drawing up the prints has us installing Schedule 80 PVC underground with sand bedding. We asked the question why Schedule 80 and not schedule 40. His reply was, because schedule 80 was rigid and schedule 40 was not. He would be okay with schedule 40 but, we would have to cover it with a flowable fill or concrete this way it would be protected from damage. We sent him the code reference for PVC (Article 352) and he came back with, schedule 40 underground and it needs to be covered with flowable fill not sand.
Is there any way, to get the NEC reference 352 (G) to spell out Schedule 40 can be installed underground with native fill, sand bedding, or concrete encasement? Instead he is reading underground encased in concrete is the only way you can install it. His reply to our questions was; Schedule 40 shall be used in lieu of Schedule 80 for the duct banks.
How can we get the Code reference changed, to be more descriptive of the back fill? ie... Schedule 40 approved for direct bury / underground with native soil, sand bedding or concrete encased back fill.
Is there any way, to get the NEC reference 352 (G) to spell out Schedule 40 can be installed underground with native fill, sand bedding, or concrete encasement? Instead he is reading underground encased in concrete is the only way you can install it. His reply to our questions was; Schedule 40 shall be used in lieu of Schedule 80 for the duct banks.
How can we get the Code reference changed, to be more descriptive of the back fill? ie... Schedule 40 approved for direct bury / underground with native soil, sand bedding or concrete encased back fill.