Interesting situation we had last week. We are running 20’ lengths of 4” sch 40 pvc in trenches with chairs and EMT tie down stakes. We have different configurations with 4 or more conduits. Most of the runs are roughly 300’ long and tie into concrete man holes at either end. The manholes have cast in place terminators that we glue into. Because we have a set point at either end, we have to use a slip coupling some where in the run. That is glued in place after the pipe is cut to length.
Last week we had some pretty warm weather for April in Michigan (80s and sun during the day, 50’s at night) we finished some runs in the afternoon, hottest time of the day. When we came back in the morning the pipe had contracted back 4-5” and pulled out of the slip couplings. Must be the weakest link. We repaired in the morning (coolest part of the day) and monitored other runs and locations.
In the afternoon sun that same run heated up and expanded again and the only place it could go was up so. Some of the chairs and stakes broke to allow for expansion as the pipes moved in the trench. In some runs there are bends and those seem to take the expansion/contraction better. Most runs are straight pipe without much flexibility. With these temperature changes pvc is expected to change in length about 1.4” per 100’ which it definitely is doing.
We are installing thousands of feet per day and unfortunately we sometimes have to wait days for concrete or backfill. With those temperature swings this will continue to be a problem.
I’ve never heard of an underground rated expansion join. Is there?
Has anyone dealt with this before? We have hundreds of thousands of feet to go working in every weather situation imaginable. How can I control this or prevent damage?
Your experiences, expertise and advice is greatly appreciated.
Last week we had some pretty warm weather for April in Michigan (80s and sun during the day, 50’s at night) we finished some runs in the afternoon, hottest time of the day. When we came back in the morning the pipe had contracted back 4-5” and pulled out of the slip couplings. Must be the weakest link. We repaired in the morning (coolest part of the day) and monitored other runs and locations.
In the afternoon sun that same run heated up and expanded again and the only place it could go was up so. Some of the chairs and stakes broke to allow for expansion as the pipes moved in the trench. In some runs there are bends and those seem to take the expansion/contraction better. Most runs are straight pipe without much flexibility. With these temperature changes pvc is expected to change in length about 1.4” per 100’ which it definitely is doing.
We are installing thousands of feet per day and unfortunately we sometimes have to wait days for concrete or backfill. With those temperature swings this will continue to be a problem.
I’ve never heard of an underground rated expansion join. Is there?
Has anyone dealt with this before? We have hundreds of thousands of feet to go working in every weather situation imaginable. How can I control this or prevent damage?
Your experiences, expertise and advice is greatly appreciated.