Do you see any problem in running 1" pvc tied ontop of the metal wire grid upon which 4" of concrete is poured, making the floor of a building?
Table 300.5 allows a zero minimum cover requirement for nonmetallic raceways "under a building".
Pvc in the cement pour is not quite under the building, so I wonder could it be allowed?
Thanks