O OHM Electrical New User Location Texas Occupation Electrical contractor Mar 19, 2025 #1 In a new patio concrete slab, does pvc schedule 40 need to be buried? Or can the pvc be on top of the ground?,since it’s going to be encased with concrete.
In a new patio concrete slab, does pvc schedule 40 need to be buried? Or can the pvc be on top of the ground?,since it’s going to be encased with concrete.
LarryFine Master Electrician Electric Contractor Richmond VA Location Henrico County, VA Occupation Electrical Contractor Mar 20, 2025 #2 Welcome to the forum. Either.
don_resqcapt19 Moderator Staff member Location Illinois Occupation retired electrician Mar 20, 2025 #3 Assuming the concrete is at least 4" thick it can be directly below the concrete.