mstrlucky74
Senior Member
- Location
- NJ
So NECA labor unit has 4" pvc at about 4 hours per hundred which is awfully low. You guys think that's attainable?
I think you need to factor in more details of the application, there may be times it isn't attainable and other times you actually go beyond a hundred in 4 hours.So NECA labor unit has 4" pvc at about 4 hours per hundred which is awfully low. You guys think that's attainable?
So NECA labor unit has 4" pvc at about 4 hours per hundred which is awfully low. You guys think that's attainable?
Sounds low....Why are you using NECA?
Does NECA indeed show 4 hours per 100 feet? This excerpt says "14" hrs/100' for 4" sched 40. (16.8 for sched 80.)
http://championfiberglass.com/wp-co.../CHAM-9581-NECA-Labor-Rate-Chart-a_0331-1.pdf
Now, 3/4" is another matter.