What are the requirements for running PVC in a concrete slab to feed a subpanel. All I can find is 300.5 note 2.
is that it? just 2" envelope?
Either as far as this discussion is concerned.SCH 40 or 80?
You're welcome but, I do need to say that if this is in a chapter 5 installation there may be more to consider, what type of facility is this sub-panel going in?Thanks
OK, you can disregard post #6.commercial building mostly offices, they are expanding the existing building
We usually scratch it into the gravel so the conduit isn't in the concrete. Less chance of it being hit if they decide to saw the concrete one day...