I am upgrading a service to add a common panel in a multi family unit. House has an underground feed and all meters have to be moved outside. I was going to go from tee box, up and out through sill plate, into meter socket and back through into panels. Inspector informed me that I have to install a disconnect before going through sill plate to outside. I cannot find this in code book. A little guidance is needed.