So I have job in a high rise 75 apts 10 on each floor
The owners want to put in Electric stoves and pay for them
So what I proposed and I think should be ok is putting a panel in on each floor in the stair case ( all working spaces met) then from the panel run a ckt to each apartment and install a disconnect and receptacle in each apartment.
My question is in regards to the panel in the stair case. I was concerned that not having a means of disconnect in the apartment would be a violation.
Two questions
1 is the panel on in the stair case in regards to Tennant access
2. Do I need a disconnect in each apartment or does the cord and plug satisfy the requirements
Sent from my SM-G965U using Tapatalk
The owners want to put in Electric stoves and pay for them
So what I proposed and I think should be ok is putting a panel in on each floor in the stair case ( all working spaces met) then from the panel run a ckt to each apartment and install a disconnect and receptacle in each apartment.
My question is in regards to the panel in the stair case. I was concerned that not having a means of disconnect in the apartment would be a violation.
Two questions
1 is the panel on in the stair case in regards to Tennant access
2. Do I need a disconnect in each apartment or does the cord and plug satisfy the requirements
Sent from my SM-G965U using Tapatalk