Question on Temp. Lighting

Status
Not open for further replies.

biggscott

New member
On the job site they have cut the plugs off of the temp. lights and spliced together the power cord and another light fixture with its plug cut also. After the splice they wrapped the cord in electrical tape and tie wrapped the cords to the hand rails on the tower. They have ran the lights on a tower and I was concerend if this was per code? Please help.
 

ceb58

Senior Member
Location
Raeford, NC
On the job site they have cut the plugs off of the temp. lights and spliced together the power cord and another light fixture with its plug cut also. After the splice they wrapped the cord in electrical tape and tie wrapped the cords to the hand rails on the tower. They have ran the lights on a tower and I was concerend if this was per code? Please help.

Can you say OSHA inspector boys and girls? Do you think it is code compliant to alter a mfg. design? I have seen the OSHA inspector give carpenters a choice when they found nicked drop cords that they had taped. Cut the cords up and throw in dumpster and go buy the OSHA rated cords or pay $500.00 per cord in fines and he would be back to check the job site the next day.
 

dnem

Senior Member
Location
Ohio
As much as we look to the NEC to do our various different jobs, sometimes the answer is elsewhere. . You have already been directed to OSHA and I want to add an experience that supports that thought.

When I first started as an inspector, I went into a number of 2 story houses for rough inspections and found that up on the second floor there were large open dropoffs to the first floor or even to the basement.

One time I was checking ceiling lighting and smoke detector Romexs thru the joists/rafters while crossing a second floor hallway bridge that was to eventually get railings on the edge looking out over the 2 story great room to the one side and railings on edge looking out over the 2 story foyer on the other side. . So during the inspection I was walking down a bridge with dropoffs on either side and no corresponding edge bounderies across the joists above. . As I walked forward checking the multiple recessed can lights above, I partially lost my "feel" for the walkway. . My heel came down on a thin flat scrap board but my toes traveled an extra inch or so farther down to the plywood walkway itself. . For the split second it took my toes to hit wood, I thought I had just stepped off the edge and the wave of fear was unexpected and intense.

I never again inspected another rough that had openings larger than 6' wide with no railing of some kind. . For my safety and that of the tradesmen working on those houses, the railings needed to be up and it wasn't the NEC that kept me from inspecting unsafe houses. . It was OSHA. . As an employee of the county, I also fall under OSHA protections and tell the general contractors/builders that fact.

If it's not safe, don't do it. . Code article or not, if your gut says "No", then you should say "No" outloud.
 
Status
Not open for further replies.
Top