Quick 15kv Labor Unit

Status
Not open for further replies.

mstrlucky74

Senior Member
Location
NJ
Have a 1/C #2 15kv wire standard install in conduit overhead. Use about 16-20 hours per thousand. Someone else told me 50-55 which seems very high. Any thoughts? Thanks.
 