Designer69
Senior Member
hey guys, quick little situation came up at work today... the guys on the field want some 120 power only for some control I&C stuff power.
so what they want to do is take 120 off of panel "A" from one of the breakers only and run that to panel "B" and jump the bus bars so that one pole is powering both busses.
they were told to use good engineering practice and not do that but for my own education I was wondering what would happen.
Thanks
so what they want to do is take 120 off of panel "A" from one of the breakers only and run that to panel "B" and jump the bus bars so that one pole is powering both busses.
they were told to use good engineering practice and not do that but for my own education I was wondering what would happen.
Thanks