On what? Someone qualified to do so should decide just what area needs to be classified and put that on a set of drawings, or document it in some other way.Pushpin said:My customer is wanting a kiosk building between 2 ethanol unloading rail spurs. There will be 10 cars on each track with the building in the middle.
The building will be 48" above finish grade.
It appears to be outside of the classified area.
Got any opinions?
Pushpin said:I agree! But...By the code will it be in or out?
One of the reasons I didn't chime in earlier is Bob's (petersonra) responses are basically correct although they could have been a bit more charitable.iwire said:Gentlemen, if you do not want to be helpful then don't bother posting.
Pushpin, someone will likely chime in with a helpful answer give it some time.
I apologize for being insufficiently charitable.rbalex said:One of the reasons I didn't chime in earlier is Bob's (petersonra) responses are basically correct although they could have been a bit more charitable.
I'm not sure, but local building and zoning codes may come into effect as well. I hope you have a good architect or engineer that is familiar with the project to work this out with.rbalex said:One of the reasons I didn't chime in earlier is Bob's (petersonra) responses are basically correct although they could have been a bit more charitable.
I guess I should simply add this: there is insufficient information in the OP to answer the question. No distances other than the elevation were mentioned. The method of material transfer also affects the answer.
In addition, the NEC just doesn?t answer the question at all. The proper Standard(s) is (are) NFPA 30, NFPA 497 or possibly, API RP500
A qualified person, knowledgeable of the whole installation should document the electrical area classification ? then the OP can be answered.
Some railroads also have requirements that can be a little unusual. I know that a place I used to work had a RR track come into the building and there was a requirement from the RR that nothing could be located within 8 or maybe it was 10 feet of the tracks.DanZ said:I'm not sure, but local building and zoning codes may come into effect as well. I hope you have a good architect or engineer that is familiar with the project to work this out with.