I know this might be odd (or maybe not?), but I was considering requesting a 480/240 single phase service for a building. I will have multiple pieced of equipment, all running 240V, and all my lights running 240V. Basically I have very minimal 120V loads and considering just installing a 5kva transformer for 120V and eating the costs to keep it energized.
Mainly I want to have my place "over wired" so when comes time for more power, the power company just needs to install a bigger transformer. I was going to get a 400A service. I realize I can just get 800A of 240V but that is twice the wire, well twice everything really.
Or does 480V single phase gear command a premium being that it is less common? I planned to just run two, 200A panels with 4/0 Al triplex.
Anything else to consider on a 480V service or system? I realize the dangers of 480V.
Mainly I want to have my place "over wired" so when comes time for more power, the power company just needs to install a bigger transformer. I was going to get a 400A service. I realize I can just get 800A of 240V but that is twice the wire, well twice everything really.
Or does 480V single phase gear command a premium being that it is less common? I planned to just run two, 200A panels with 4/0 Al triplex.
Anything else to consider on a 480V service or system? I realize the dangers of 480V.