I have cell tower site with monopole tower. On ground are cabinets with rectifiers whose AC sides are fed by feeder breaker panelboard.
DC side feeds antennas, ray caps, the, etc etc equipment on monopole tower
I am reviewing plans which call for demand and load calculation for the AC panelboard at cell site and I looked into NEC 2014 Section 220 but there is no demand factor for it.
Anyone doing cell tower work does anyone know what they use for demand factor for AC side of rectifier? Where can this be found in NEC 2014?